| New Transmission Centre |
 |
| Client: |
Redbull F1 Racing Team |
| Service: |
Chilled Water Transmission Cooling |
| Value: |
140k |
| Date: |
| November 2006 |
Duration: |
12 Weeks |
|
|
 |
 |
| Supply and installation of new chilled water unit, complete with packaged pumps and integrated building management system. The completed installation provides close controlled chilled cooling water to the testing rigs and transmission systems within the new state of the art Redbull Formula 1 transmission test facility. |
 |
|
|
 |
|
|
 |
| New Kitchens, Radley College, Abingdon, Oxon |
 |
| Client: |
Radley College |
| Service: |
Heating, Plumbing and Ventilation |
| Value: |
- |
| Date: |
| 2004 |
Duration: |
38 weeks with phased handover |
|
|
 |
 |
This project involved part demolition and rebuilding of an existing Victorian Kitchen, in the heart a fully operating boys school (650 pupils) removing all ground floor supporting walls, heavy temporary work and steel framing and installation of a new kitchen and servery. A library and new student room were built on a new first floor.
A temporary kitchen was procured adjacent to the site and 3,000 meals served daily for the duration of the project. |
 |
|
|
 |
|
|
|
 |
 |
|
|
|
|